One buoy per line is required unless lightening buoys (spring buoys) are used to avoid line contact with

obstruction on the bottom. Piggyback anchors may be used depending on the bottom type or to increase the

load admittance on anchors. Chain can also be provided, to be installed between anchors and wire cable to

increase the holding on seabed.

On the SMV, no specific mobilisation required, unless the subsequent operation itself requires extra

equipment.

Arrived on the field, if

S

ite Mana

g

er

authorises the operation and if weather conditions are within the agreed

limits, the anchor deployment may start.

The AH vessel usually has the positioning system on board to know where to drop the anchors and where

are the obstructions.

The SMV will hold a constant position as far as practicable at the safety position while the AH vessel deploys

the anchor lines.

Once all anchors have been deployed and all pig tail’s marking buoys are plotted on the radar, a tension test

of 30 minutes minimum will be done to confirm the proper setting of anchors, according to international rules

chapter 10.4.6.3 of ISO 19901-7-2005

. Alternatively, upon charterer procedure, it’s usually agreed that three

times the anchor weight

should

be applied on each line. During tension test the AH Vessel will make a round

trip to check that there is no change of position on pig tail’s marking buoys.

If the test is passed, then the SMV may stop her engines and move to working position heaving and slacking

on her lines. The lines will be used to change position for the rest of the operation, unless weather imposes

to start engine as back-up. Propulsion

shall

also be kept running if the ship is to approach very close to the

structure provided that no divers are in the water.

Pig Tail

Obstruction

Piggy Back

Anchor

Version 04. Original date: 22/06/2012. Version date: 31/12/2014. Valid version only on QMS site. Uncontrolled document when printed.

Procedure prepared by: BOS Operations Department Project Coordinator. Approved by: Head of Operations. Validated by: BOS Quality Representative