BOS-PRD-07.900607

d) That procedures include requirement for operational meetings between all parties; particularly

anchor handling vessels, to ensure that the content of mooring plans and necessary communications

are fully understood.

Ri

g

Move Master

has the responsibility, authority and accountability for:

a) Monitoring the spread mooring operations.

4

D

escri

p

tion

4

.1

S

a

f

et

y p

reca

u

tions

d

u

rin

g

m

oorin

g

o

p

erations

The mooring operation on any ship is potentially dangerous. Crewmembers are at greater risk of injury

during mooring and unmooring operations than at any other time.

The mooring operations

shall

be subject to full pre-job planning Job Safety Analysis (JSA) before

commencing, giving full consideration to the effects of weather, sub-sea obstructions and vessel movement.

Affiliate Organisations have formal procedures that require shore management oversight of spread mooring

plans and operations.

The following are some safety reminders, which need to be observed during mooring operations:

x

DO NOT surge synthetic fibre ropes on drum ends. This may damage the rope and also leave

deposits on the drum end or bits, causing the rope to jump with the risk of injury to persons nearby;

x

DO NOT stand too close to a winch drum or bit when holding and tensioning a line. If it surges you

could be drawn into the drum or bit before you can safely take another hold or let go;

x

DO NOT apply too many turns on a drum end. No more than 4 turns

should

be taken with synthetic

lines. If more turns are applied then it is difficult to release in a controlled manner;

x

DO NOT bend/twist rope excessively;

x

DO NOT stand in the bight of any rope. BEWARE OF THE BIGHT;

x

DO NOT stand close to a rope under load. It may part without warning. KEEP OUT OF THE

SNAPBACK ZONE;

x

DO NOT leave loose objects in the line handling area. If a line breaks it may throw such objects

around as it snaps back;

x

DO NOT have more people than necessary in the vicinity of a line;

x

DO NOT attempt to handle a wire or rope on a drum end, unless a second person is available to

remove or feed the slack rope to you;

x

DO NOT leave winches running unattended;

x

DO NOT stand on winches/bollards to get a better view;

x

DO NOT use wire direct from a stowage reel that has not been designed to withstand loads;

x

DO NOT allow oil leaks from winches to make the deck hazardous. It could be you who slips and

falls;

x

DO WEAR the correct safety clothing and equipment;

x

DO WEAR gloves when handling wires;

x

DO LEARN ABOUT the mooring system on your ship;

x

DO ANTICIPATE AND PREVENT potentially dangerous situations arising;

x

DO TAKE CARE.

Version 04. Original date: 22/06/2012. Version date: 31/12/2014. Valid version only on QMS site. Uncontrolled document when printed.

Procedure prepared by: BOS Operations Department Project Coordinator. Approved by: Head of Operations. Validated by: BOS Quality Representative

6 / 19